* add release trigger Signed-off-by: Alex Goodman <alex.goodman@anchore.com> * deduplicate version and changelog calls + add gh checks Signed-off-by: Alex Goodman <alex.goodman@anchore.com> * add more chronicle verbosity, but not when triggering releases Signed-off-by: Alex Goodman <alex.goodman@anchore.com> * bump chronicle version to get --version-file feature Signed-off-by: Alex Goodman <alex.goodman@anchore.com> * update bootstrap tool workflow to include glow Signed-off-by: Alex Goodman <alex.goodman@anchore.com> * add version prefix check on tags in release quality gate Signed-off-by: Alex Goodman <alex.goodman@anchore.com> --------- Signed-off-by: Alex Goodman <alex.goodman@anchore.com>
This commit is contained in:
+28
-28
@@ -4,8 +4,7 @@ A good release process has the following qualities:
|
||||
|
||||
1. There is a way to plan what should be in a release
|
||||
1. There is a way to see what is actually in a release
|
||||
1. Allow for different kinds of releases (major breaking vs backwards compatible
|
||||
enhancements vs patch updates)
|
||||
1. Allow for different kinds of releases (major breaking vs backwards compatible enhancements vs patch updates)
|
||||
1. Specify a repeatable way to build and publish software artifacts
|
||||
|
||||
## Planning a release
|
||||
@@ -21,10 +20,7 @@ completed, would allow the release to be considered complete. A Milestone is onl
|
||||
|
||||
Not all releases need to be planned. For instance, patch releases for fixes should be
|
||||
released when they are ready and when releasing would not interfere with another current
|
||||
release (where some partial or breaking features have already been merged). Beta releases
|
||||
and release candidates should not be independently planned from the non-beta release. That
|
||||
is, the features for a `v0.1-beta.1` release should be planned under the `v0.1` Milestone,
|
||||
not under a separate `v0.1-beta.1` Milestone.
|
||||
release (where some partial or breaking features have already been merged).
|
||||
|
||||
Unless necessary, feature releases should be small and frequent, which may obviate the
|
||||
need for regular release planning under a Milestone.
|
||||
@@ -42,9 +38,9 @@ Changelog line. Furthermore, there should be a place to see all released version
|
||||
release date for each release, the semantic version of the release, and the set of changes
|
||||
for each release.
|
||||
|
||||
This project auto-generates the Changelog contents for each current release and posts the
|
||||
generated contents to the GitHub Release page. Leveraging the GitHub Releases feature
|
||||
allows GitHub to manage the Changelog on each release outside of the git repository while
|
||||
**This project auto-generates the Changelog contents for each current release and posts the
|
||||
generated contents to the GitHub Release page**. Leveraging the GitHub Releases feature
|
||||
allows GitHub to manage the Changelog on each release outside of the git source tree while
|
||||
still being hosted with the released assets.
|
||||
|
||||
The Changelog is generated from the metadata from in-repository issues and PRs, using
|
||||
@@ -60,8 +56,8 @@ The above suggestions imply that we should:
|
||||
- The appropriate label is applied to PRs and/or issues to drive specific change type
|
||||
sections (deprecated, breaking, security, bug, etc)
|
||||
|
||||
With this approach as we cultivate good organization of PRs and issues we automatically
|
||||
get an equally good Changelog.
|
||||
**With this approach as we cultivate good organization of PRs and issues we automatically
|
||||
get an equally good Changelog.**
|
||||
|
||||
## Major, minor, and patch releases
|
||||
|
||||
@@ -69,8 +65,8 @@ The latest version of the tool is the only supported version, which implies that
|
||||
parallel release branches will not be a regular process (if ever). Multiple releases can
|
||||
be planned in parallel, however, only one can be actively developed at a time. That is, if
|
||||
PRs attached to a release Milestone have been merged into the main branch, that release is
|
||||
now the "next" release. This implies that the source of truth for release lies with the
|
||||
git log and Changelog, not with the release Milestones (which are purely for planning and
|
||||
now the "next" release. **This implies that the source of truth for release lies with the
|
||||
git log and Changelog, not with the release Milestones** (which are purely for planning and
|
||||
tracking).
|
||||
|
||||
Semantic versioning should be used to indicate breaking changes, new features, and fixes.
|
||||
@@ -81,24 +77,28 @@ instead the minor version indicates both new features and breaking changes.
|
||||
|
||||
Ideally releasing should be done often with small increments when possible. Unless a
|
||||
breaking change is blocking the release, or no fixes/features have been merged, a good
|
||||
target release cadence is between every 2 or 4 weeks.
|
||||
target release cadence is between every 1 or 2 weeks.
|
||||
|
||||
This release process itself should be as automated as possible, and have only a few steps:
|
||||
This release process itself should be as automated as possible, and has only a few steps:
|
||||
|
||||
1. Tag the main branch with a full semantic-version, prefixed with a `v`. If there is a
|
||||
milestone with a partial version, the full version should be used for the git tag (e.g.
|
||||
with a Milestone of `v0.1` the tag should be `v0.1.0`). You can determine the changes going
|
||||
into a release by running `make changelog-unreleased`. Use this change list to determine the
|
||||
release increment. After determining the release increment (major, minor, patch), create the tag.
|
||||
Given the above example the command to create the tag would be `git tag v0.1.0`.
|
||||
1. **Trigger a new release with `make trigger-release`**. At this point you'll see a preview
|
||||
changelog in the terminal. If you're happy with the changelog, press `y` to continue, otherwise
|
||||
you can abort and adjust the labels on the PRs and issues to be included in the release and
|
||||
re-run the release trigger command.
|
||||
|
||||
1. Push the tag. Given the above example the command to push the tag would be `git push origin v0.1.0`.
|
||||
|
||||
1. A release admin must approve the release on the GitHub Actions release pipeline run page.
|
||||
Once approved, the release pipeline will generate all assets and draft a GitHub Release.
|
||||
|
||||
1. Navigate to the GitHub Release draft page to review the final changelog and publish the
|
||||
release. Once published, a release-follow-up pipeline will publish derivative artifacts
|
||||
(docker image to DockerHub, brew formula to the external homebrew git repo, etc).
|
||||
Once approved, the release pipeline will generate all assets and publish a GitHub Release.
|
||||
|
||||
1. If there is a release Milestone, close it.
|
||||
|
||||
## Retracting a release
|
||||
|
||||
If a release is found to be problematic, it can be retracted with the following steps:
|
||||
|
||||
- Deleting the GitHub Release
|
||||
- Untag the docker images in the `ghcr.io` and `docker.io` registries
|
||||
- Revert the brew formula in [`anchore/homebrew-syft`](https://github.com/anchore/homebrew-syft) to point to the previous release
|
||||
|
||||
**Note**: do not delete release tags from the git repository since there may already be references to the release
|
||||
in the go proxy, which will cause confusion when trying to reuse the tag later (the H1 hash will not match and there
|
||||
will be a warning when users try to pull the new release).
|
||||
|
||||